10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

These 10 free AI questions are organized by exam domain, so you can see how each part of the National Board Authorized Inspector Commission (AI) blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Responsibilities and Duties of the AI

Question 1

By purchase order, an outside engineering firm accepts liability for errors in the design calculations it supplies to a vessel Manufacturer. The AI discovers that a specified nozzle load was omitted. Under the construction Code, which party still bears responsibility for ensuring that the completed vessel design complies?

Show answer & explanation

Correct answer: A - The vessel Manufacturer.

Domain 2: Boiler and Pressure Vessel Types and Terminology

Question 2

An electrically heated boiler will supply process water at 145 psig and an outlet temperature of 270°F. No steam is delivered. Which construction classification applies to these specified service conditions?

Show answer & explanation

Correct answer: A - Section I: a high-temperature-water boiler because the outlet exceeds 250°F.

Domain 3: Code Structure and Content

Question 3

On the approved Code-boundary drawing, a steam-piping spool lies within the boiler external piping of a Section I power boiler. The inspection plan must identify both its technical construction rules and its certification requirements. How should those responsibilities be assigned?

Show answer & explanation

Correct answer: A - B31.1 supplies the technical construction rules; Section I retains inspection and certification jurisdiction.

Domain 5: Design

Question 4

A Type 1 longitudinal butt joint in a Section VIII, Division 1 shell has passed the specified UW-11(b) spot radiography, but the shell calculation uses E = 1.00. No service, material, or thickness rule requires full radiography. To retain the agreed examination plan, what should the AI require in the design review?

Show answer & explanation

Correct answer: C - Use E = 0.85 and verify the shell thickness with the revised calculation.

Question 5

A cylindrical shell has P = 300 psi, corroded inside radius R = 24.0 in., allowable stress S = 20,000 psi, and joint efficiency E = 0.85. Its internal corrosion allowance is 0.125 in. For the controlling hoop-stress check, use t = PR/(SE - 0.6P), where t excludes corrosion allowance. The minimum measured thickness after forming is 0.580 in. All other design and fabrication checks are satisfactory. Which thickness assessment is correct?

Show answer & explanation

Correct answer: D - Accept: the required finished thickness is approximately 0.553 in.

Domain 6: Materials

Question 6

Four shell blanks carry coded marks rather than the plate mill's original heat-number stamp. The marks were applied before cutting under an identification system accepted by the AI. Each code has a verified link through the cutting plan to the original plate and its matching material test report. On the question of material identification, the AI should:

Show answer & explanation

Correct answer: B - Accept the coded marks and their verified records as material identification.

Domain 7: Fabrication

Question 7

A welding procedure qualified without notch-toughness testing is proposed for a new vessel whose procedure must be impact-qualified. The process and base-metal combination are unchanged. The existing PQR records tensile and bend results, but no impact results; the original coupon is no longer available. Before issuing the WPS for this job, the welding engineer needs to:

Show answer & explanation

Correct answer: C - Qualify a procedure with the required impact tests and supplementary essential variable controls.

Domain 8: Nondestructive Examination

Question 8

After grinding a repair excavation in a nonferromagnetic austenitic stainless-steel head, a technician reports a negative magnetic particle examination. A fine surface-breaking crack is still suspected. The repair procedure permits an appropriate surface method. Which examination is best suited to check the excavation for the remaining crack?

Show answer & explanation

Correct answer: D - Liquid penetrant examination of the cleaned, dry excavation.

Domain 9: Testing and Heat Treatment

Question 9

During the staged pneumatic test of a new pressure vessel, a hissing leak develops at a bolted test closure. The vessel is still pressurized, and a fitter starts toward the closure with a wrench. Remote isolation and controlled venting are available outside the barricade. What is the immediate priority?

Show answer & explanation

Correct answer: B - Keep personnel clear, isolate the gas supply, and depressurize remotely before intervention.

Domain 10: Calibration of Measurement and Test Equipment (M&TE)

Question 10

During an as-found calibration, a 0-300 psi working gauge gives reference/indicated readings of 60/62, 150/149, and 240/242 psi. The controlled procedure allows ±1% of full scale at each point; its measurement-uncertainty rule and all other checks are satisfied. A technician flags the first point because its error exceeds 1% of the reference reading. What disposition follows from the specified tolerance?

Show answer & explanation

Correct answer: C - Accept without adjustment; each error is within ±3 psi.

The rest of the AI blueprint

The AI exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more AI questions with explanations.

Continue in the free practice test →

View plans